Based on over 30 years’ experience with project risk management, the best way I found to monitor risk mitigation plans is to incorporate them into the Integrated Master Schedule (IMS). The reason is each month (or week) when the IMS is reviewed the risk mitigation plan is also reviewed. Since the IMS is linked, a slip in a mitigation plan step can readily be seen as well as the potential impact it may have on the project.
The question is How is the risk mitigation plan integrated into the IMS? This paper will explain how it tis done. [Read more…]